• Update for the week of July 5th
  1. All basic structural members are up
  2. Working on the roof over the lobby
  3. Bringing in sub-grade / hoping to pour lobby floor
  4. Roofing the rest of building – end of the week
  5. Duct work for lobby should be started end of the week
  6. Interior walls for lobby will be next